Lead times (without shipping time) - October 2022
Product Quantity Current Lead
Time (weeks)
Lead Time
(Aug. 2022)
Controls
IP20 I/O system X20BM* / X20TB* / X20DI* / X20DO* / X20AI* / X20AO* 40 40
IP20 I/O system rest (included PLC X20CP*) 52 52
X20 safety X20S* 52 52
X20 coated 52 52
X20 sets X20:* / X20Z* / X20A:* 1-100 pcs 52 52
« 101-500 pcs 52 52
« >500 pcs 52 52
IP67 system X67* 40 40
X90 1 - 50 pcs. 40 40
X90 >50 pcs. 40 40
Controls + HMI
Power Panels C and T 4PPC* / 6PPT* 48 48
Power Panels C-/T-Panels 4PPC* / 6PPT* custom mylar 48 48
Power Panel 65 4PP065* 52 52
Compact Systems 52 52
Vision Systems (smart sensor and smart camera)
Vision Systems VS* / VA* / VS* / VC* 1 - 2 pcs 8 8
« 3 - 5 pcs 9 9
« 6 - 10 pcs 10 10
Site Manager (remote maintenance)
Site Manager accessories: antenna 0RMSM.A* 12 12
Site Manager 0RMSM11* 12 12
HMI
Panelware 4A* / 4B* / 4PW* 50 50
Mobile Panels 5MP* 50 50
APC910 5Y* 1-15 pcs 50 50
« 16 - 50 pcs 50 50
« 51 - 100 pcs 50 50
B&R tries to deliver the respective products according to below indicative lead times, but we
cannot bindingly commit to such dates which can be changed at any time.
BnR Standard Delivery Lead Times 2022 October.xlsx Page 1 of 5Lead times (without shipping time) - October 2022
Product Quantity Current Lead
Time (weeks)
Lead Time
(Aug. 2022)
B&R tries to deliver the respective products according to below indicative lead times, but we
cannot bindingly commit to such dates which can be changed at any time.
APC2100 5V* / APC2200 5R* 1-15 pcs 50 50
« 16 - 50 pcs 50 50
« 51 - 100 pcs 50 50
APC3100 5S* 1-15 pcs 50 50
« 16 - 50 pcs 50 50
« 51 - 100 pcs 50 50
PPC900 5Z* / PPC2100 5W* / PPC2200 5Q* / PPC1200 5F* 1-15 pcs 50 50
« 16 - 50 pcs 50 50
« 51 - 100 pcs 50 50
PPC3100 5T* 1-15 pcs 50 50
« 16 - 50 pcs 50 50
« 51 - 100 pcs 50 50
Automation Panels 5AP* (included custom devices) 50 50
Motion
ACOPOStrak 0 - 10 m On request On request
« 11 - 50 m On request On request
« 51 - 100 m On request On request
« > 100 m On request On request
SUPERtrak 22 22
ACOPOS 8V1010* / 8V1090* 1-30 pcs 50 50
« 31-100 pcs 50 50
ACOPOS 8V1180* / 8V128M* 1-15 pcs 50 50
« 16-50 pcs 50 50
« >50 pcs On request On request
ACOPOS coated 8V1010* / 8V1090* 1-10 pcs. 50 50
« 11-30 pcs. 50 50
« 31-100 pcs. 50 50
ACOPOS coated 8V1180* / 8V128M* 1-5 pcs. 50 50
« 6-15 pcs. 50 50
BnR Standard Delivery Lead Times 2022 October.xlsx Page 2 of 5Lead times (without shipping time) - October 2022
Product Quantity Current Lead
Time (weeks)
Lead Time
(Aug. 2022)
B&R tries to deliver the respective products according to below indicative lead times, but we
cannot bindingly commit to such dates which can be changed at any time.
« 16-50 pcs. 50 50
ACOPOS P3 8EI* / 8EC* 1-30 pcs 52 52
« 31-100 pcs 52 52
ACOPOSmulti wall mounting 8BVIxxxxHW* ≤ 22 A
8BVI0014HW, 8BVI0028HW*, 8BVI0055HW*, 8BVI0110HW*, 8BVI0220HW* 40 40
ACOPOSmulti wall mounting 8BVIxxxxHW* ≥ 33 A
8BVI0330HW*, 8BVI0440HW*, 8BVI0660HW*, 8BVI0880HW*, 8BVI1650HW* 40 40
ACOPOSmulti cold plates '8BVIxxxxHC' 40 40
ACOPOSremote 8CV* 52 52
ACOPOSmicro 80V* / 80PS* 50 50
ACOPOSinverter S44* / X64* / P74* / P84* On request On request
ACOPOSinverter P66* / P76* / P86* 1 - 10 pcs 52 52
« 11 - 30 pcs 52 52
« > 30 pcs 52 52
ACOPOSinverter P96* On request On request
Customer specific products
Quantity contract first shipment 52 52
Call off order from quantity contract 52 52
Single-order w/o quantity contract 52 52
All other products 52 52
Accessories (cables,....) As corresponding product group As corresponding product group
Discontinued products On request On request
Motors with integrated servo drive
ACOPOSmotor '8DI3' / '8DI4' / '8DI5' 52 52
ACOPOSmotor '8DI3' / '8DI4' / '8DI5' with gearbox 52 52
Motors
Standard motors 8LSA (assembled in Austria) 1 - 10 pcs 52 52
« 11 - 30 pcs 52 52
Standard motors 8LSA2 / 8LSAA / 8LSA3 / 8LSA4 / 8LS5 / 8LSA7 52 52
Non standard motors 8LSA2 / 8LSAA / 8LSA3 / 8LSA4 / 8LSA5 / 8LSA6 52 52
Non standard motors 8LSA7 52 52
Non standard motors 8LSA8 52 52
BnR Standard Delivery Lead Times 2022 October.xlsx Page 3 of 5Lead times (without shipping time) - October 2022
Product Quantity Current Lead
Time (weeks)
Lead Time
(Aug. 2022)
B&R tries to deliver the respective products according to below indicative lead times, but we
cannot bindingly commit to such dates which can be changed at any time.
8LVA1 / 8LVA2 / 8LVA3 52 52
8LWA1 / 8LWA2 / 8LWA3 52 52
8LVB1 / 8LVB2 / 8LVB3 52 52
8LSO9 / 8LSP9 52 52
8LSN4 / 8LSN5 52 52
8LSC4 / 8LSC5 / 8LSC6 52 52
8LSC7 52 52
8LSC8 52 52
8LSE4 / 8LSE6 52 52
8LSE8 52 52
8JS 35 52
8JSB/Q 35 52
Torque 8LTA /Q 9+C 52 52
Torque 8LTJ / S 9+C 52 52
Torque 8LTB / K 9 On request On request
8KS8 37 52
8KS9 37 52
8WS 23 52
8LW 52 52
Stepper motors 80MP 52 52
Servo motors options
Safety encoder (option S0/S1) +1 +1
Reinforced bearing (option 04/11) +2 +2
Reinforced bearing + brake +3 +3
Reinforced brake On request On request
8LSC5 A/B/C ("Cigarillo" length) +1 +1
Gearboxes
8GP40 / 8GF40 / 8GA40 / GP45 5 52
8GA45 / 8GP50 / 8GA50 / 8GP55 5 52
BnR Standard Delivery Lead Times 2022 October.xlsx Page 4 of 5Lead times (without shipping time) - October 2022
Product Quantity Current Lead
Time (weeks)
Lead Time
(Aug. 2022)
B&R tries to deliver the respective products according to below indicative lead times, but we
cannot bindingly commit to such dates which can be changed at any time.
8GP60 / 8GF60 / 8GA60 / 8GP65 / 8GA65 5 52
8GA55 / 8GP70 / 8GF70 / 8GA75 5 52
Reduced backlash ("R") option +1 +1
Motor with assembled gearbox lead time motor +1 lead time motor +1